Quick answer. Class Deviation 2026-O0025, Revision 3 is the acquisition-side instrument that carries the July 13 Phase 2 suspension into contracting practice. It tells contracting officers to remove or revise CMMC requirements that go beyond self-assessment, and it leaves the rest of the machinery in place: the CMMC clause, the SPRS check before award, DFARS 252.204-7012, and NIST SP 800-171 Revision 2 by name.

What the document is

It is a memorandum to the military departments and defense agencies titled "Class Deviation - Revolutionary Federal Acquisition Regulation (FAR) Overhaul Part 40, Defense FAR Supplement (DFARS) Part 240". Its opening paragraph says it takes effect immediately and "revises and supersedes Class Deviation 2026-O0025, Revision 2, issued on July 16, 2026". The copy we read is 83 pages and was digitally signed on 3 September 2026 by the Principal Director, Defense Pricing, Contracting, and Acquisition Policy.

Most of those pages are not about CMMC. The deviation replaces the codified text of FAR Part 40 and DFARS Part 240 for contracting purposes, and this revision also deals with prohibited sources and other statutory items. This page covers only the CMMC and NIST SP 800-171 parts.

What it tells contracting officers to do about CMMC

Contracting officers must "collaborate with requiring activities to remove or revise" CMMC requirements in new and existing solicitations and contracts, in accordance with the DoW CIO memorandum of 13 July 2026. The deviation then lists what that memorandum does:

  • Permits requiring activities to include CMMC Level 1 (Self) or Level 2 (Self) assessments in all procurement requests and requirement documents.
  • Requires baseline compliance with NIST SP 800-171 Rev 2 in accordance with DFARS 252.204-7012.
  • Suspends the November 2026 CMMC Phase 2 transition.
  • Requires program managers and requiring activities to initiate amendments to active solicitations, and contracting officers to issue those amendments as soon as practicable.
  • For existing contracts that contain these requirements, requires removal by modification before the next option period is exercised or through the next scheduled administrative modification.

What it leaves in place

The attached DFARS Part 240 text still contains a full CMMC subpart at 240.371. Read from the attachment:

ProvisionWhat it still says
240.371-4(b)Contracting officers must check SPRS and not award to an offeror without a current CMMC status at the required level, or higher, for each CMMC UID the offeror provides
240.371-4(c)The same SPRS check applies before exercising an option or extending the period of performance
240.371-3(b)(2)Levels 2 and 3 can be conditional for no more than 180 days from the CMMC status date, and award can occur on a conditional status. Level 1 requires a final status
240.371-5(a)Clause 252.204-7021 is still prescribed. Until 9 November 2028 it applies when the program office or requiring activity determines a specific CMMC level is required; from 10 November 2028 the trigger widens to any use of contractor systems to process, store or transmit FCI or CUI
240.371-5(b)Provision 252.204-7025 goes in solicitations that include 252.204-7021
252.204-7012, as attachedNames "Revision 2" of NIST SP 800-171 in the text of the clause
252.240-7997 (FEB 2026) (DEVIATION 2026-O0025)NIST SP 800-171 DoD Assessment Requirements: Medium and High assessments conducted by Government personnel using NIST SP 800-171A

Two points are worth drawing out. First, the SPRS check at award is a contracting officer duty in this text, not a courtesy. A Level 2 (Self) status that is missing or stale blocks award where a level is specified. Second, the 2028 dates in 240.371-5(a) were not edited out. Whether they survive the reform review is unknown; what the deviation shows is that nobody has removed them yet.

What a small contractor should do with this

  1. If a live solicitation still asks for a Level 2 (C3PAO) or Level 3 assessment, the deviation says it should be amended. Ask the contracting officer in writing and cite the deviation number.
  2. If an existing contract carries such a requirement, expect removal by modification at the next option or scheduled administrative modification. Until the modification is issued, the contract says what it says. Do not treat a memo as having changed your contract.
  3. Keep your self-assessment, SPRS entry and annual affirmation current. Those are the parts the deviation keeps enforcing.
  4. Build to Revision 2. The deviated clause text and 32 CFR 170.2 both name it. See Rev 2 vs Rev 3.

For the clause numbers themselves, including how 252.204-7020 became 252.240-7997, see the DFARS clauses behind CMMC. For the suspension, see CMMC Phase 2 is suspended.

What we did not verify

  • We read the memorandum and the CMMC and 800-171 sections of its attachments, not all 83 pages line by line.
  • We did not compare Revision 3 against Revision 2 to isolate what changed between them. The memorandum says this revision "implements several statutory requirements and corrects definitions".
  • A class deviation is direction to contracting officers. It does not amend 32 CFR Part 170, which remains in force as published.

Source: Class Deviation 2026-O0025, Revision 3, memorandum and Attachment 1 (DFARS Part 240 and clause text), read in full for the sections cited on 10 November 2026. The memorandum is published by Defense Pricing, Contracting, and Acquisition Policy; obtain your own copy from the DoD class deviations page before relying on any passage. Educational material, not legal advice; your contract and your contracting officer govern.